Correct
Not quite — the correct answer is highlighted
Show answer & explanationHide answer
Answer: (B) Monday
Explanation
Correct Answer: B
Using the calendar odd days method, the number of odd days from 24 July 1999 to 24 July 2003 can be calculated over the four-year interval. Among these years, 2000 is a leap year which contributes 2 odd days, while 2001, 2002, and 2003 are ordinary years, each contributing 1 odd day.
Total odd days from 24 July 1999 to 24 July 2003 = 2 + 1 + 1 + 1 = 5 odd days.
The target date of 28 July 2003 is 4 days after 24 July 2003.
Total cumulative odd days = 5 + 4 = 9 odd days.
Dividing 9 by 7 yields a remainder of 2 odd days. Adding 2 days to Saturday results in Monday.