Answer: (A) 15 days
Explanation
The efficiency ratio of X and Y is 3:1. Because time taken is inversely proportional to efficiency, the ratio of time taken by X and Y is 1:3. Let X take k days and Y take 3k days. The difference in their time is given as 3k - k = 40 days, so 2k = 40, which means k = 20. Consequently, X takes 20 days and Y takes 60 days to complete the work alone. Using the formula for combined work T = Tₓ T_y{Tₓ + T_y}, the time taken to complete the work together is (20 × 60)/(20 + 60) = ¹²⁰⁰⁄₈₀ = 15 days.