Answer: (C) 14
Explanation
The relationship between men, days, and work is defined by the formula (M₁ × D₁)/(W₁) = (M₂ × D₂)/(W₂). Given M₁ = 7 men, D₁ = 12 days, and W₁ = 1 unit of work, we need to find the total men M₂ required for W₂ = 2 units of work in D₂ = 8 days.
(7 × 12)/(1) = (M₂ × 8)/(2)
84 = 4 × M₂
M₂ = 21
The total number of men required is 21. To find the additional men needed, subtract the original 7 men from the total: 21 - 7 = 14.